Federal OSHA’s general-industry lockout rule excludes construction employment. On jobsites, 29 CFR 1926.417 addresses electrical controls, equipment and circuits, while 1926.702(j) requires lockout and tagging during covered concrete and masonry equipment maintenance or repair when unintended operation could cause injury.
Those distinctions matter on a site where one crew is servicing a temporary distribution panel and another is repairing a concrete pump. The work, the equipment and the energy sources determine what the crew has to control. Start by identifying the task and the applicable rule, then build the isolation plan around the actual equipment.
Key Takeaways
- 29 CFR 1910.147(a)(1)(ii)(A) expressly excludes construction employment from its scope.
- Section 1926.417 requires deenergized equipment or circuits to be made inoperative and tagged at each point where they could be energized.
- Section 1926.702(j) requires all potentially hazardous energy sources to be locked out and tagged for covered concrete and masonry equipment maintenance or repair.
- Agree on who controls each isolation point, what other trades need to know and who coordinates restoration before work begins.
Does OSHA 1910.147 Apply to Construction?
Federal 1910.147(a)(1)(ii)(A) lists construction employment among the work it excludes. A company can carry useful practices from its general-industry program into its construction procedures, such as clear isolation records and shift handoffs. The applicable construction rules still govern the task.
Mixed sites make classification especially important. An expansion project inside an operating factory can bring construction crews and plant maintenance crews into the same area. Review each scope of work with the site safety lead, then agree on a common way to communicate interruptions, isolation boundaries and return to service. Our guide to OSHA standards for construction and general industry explains the broader distinction between the two sets of standards.
OSHA 1926.417: Lockout and Tagging of Circuits
OSHA 1926.417 distinguishes between deactivating controls and deenergizing equipment or circuits. Its three paragraphs cover different parts of the work.
- Paragraph (a). Tag controls that are to be deactivated during work on energized or deenergized equipment or circuits.
- Paragraph (b). Make deenergized equipment or circuits inoperative and tag each point where they can be energized.
- Paragraph (c). Place tags so they plainly identify the equipment or circuit being worked on.
In its September 28, 2006 interpretation, OSHA explains that a lock is one way to meet the inoperative requirement in paragraph (b). Other methods can qualify if they actually make the equipment or circuit inoperative, and the tagging requirement remains. Apply the employer’s approved procedure, including any stricter lock requirement it sets. A tag communicates the work in progress, while the isolation method prevents the equipment or circuit from operating.
Read this rule alongside 1926.416(a)(1), which addresses employee protection when the work brings someone close enough to contact a power circuit. The provision calls for protection against shock by deenergizing and grounding the circuit or by effective guarding. The site electrical lead should determine how that requirement applies to the work and who is qualified to carry out and verify the controls.
OSHA 1926.702(j): Concrete and Masonry Equipment
OSHA 1926.702 covers equipment and tools used in concrete and masonry construction. Paragraph (j) applies to maintenance or repair when unintended operation could injure someone. It requires crews to lock out and tag all potentially hazardous energy sources before employees perform that work. Its examples include compressors, mixers, screens and pumps used for these activities. Tags must say “Do Not Start” or carry a similar instruction.
For a pump repair, ask the equipment lead to identify the energy sources that remain relevant after shutdown. Depending on the machine, the review may need to cover electrical supply, hydraulic pressure and parts that could move. The machine’s procedure must address the actual hazards before the crew begins work. Paragraph (a)(2) also has a separate lockout and tagging requirement for the ejection system before anyone enters covered bulk cement storage facilities.
Temporary Power, Generators and Jobsite Panels
Temporary power can change as the job moves from one phase to the next. Under 1926.405(a)(2)(ii)(D), a temporary circuit must have disconnecting switches or plug connectors that allow all its ungrounded conductors to be disconnected. Before a shutdown, compare the current panel schedule and field labels with the actual equipment and feeds.
Have the qualified electrical lead confirm whether a generator, transfer equipment or another source can supply the affected circuit. OSHA’s wiring design and protection rule has separate provisions for portable and vehicle-mounted generators. A generator grounding provision does not resolve which feeds the work requires the crew to control. If labels or documentation disagree, pause the work until the electrical lead confirms the circuit boundaries and approved isolation points.
Coordinate Lockout on Multi-Employer Jobsites
A shutdown can affect electricians, equipment operators and subcontractors who work from different schedules and drawings. Give each crew current information about the equipment, the work boundary, the people protected by the isolation and the conditions for restoring service.
OSHA’s Multi-Employer Citation Policy evaluates employer roles using the facts of the site, including who creates a hazard, exposes employees to it, corrects it or controls the work. For a planned shutdown, record who coordinates the work and when each contractor must check in. Update the handoff when work scope, panels, power sources or affected crews change. The worksheet below gives supervisors three prompts to cover before release.

Match the Portable LOTO Kit to the Site
A portable kit keeps commonly used devices together when an authorized crew moves between work areas. Before issuing a kit, check three things.
- Inventory. List the isolation points the crew will need to secure.
- Device selection. Choose padlocks, hasps, breaker lockouts or plug lockouts as the procedure calls for them.
- Fit. Check the manufacturer’s fit information against the actual equipment.
TRADESAFE lockout tagout kits offer different device assortments for that selection.
Use tags that identify the equipment and communicate the restriction to the crews involved. TRADESAFE bilingual lockout tagout tags display an English and Spanish warning. For work under 1926.702(j), confirm that the selected tag meets the provision’s instruction to communicate that the equipment is not to be operated. Use the site’s procedure to determine what equipment identifiers, contacts and other details the crew needs on the tag.
The image below shows a portable electrical kit and a separate bilingual tag product. Compare each with the site’s device list and tag requirements before selecting supplies.

Make the Isolation Plan Part of the Job Briefing
Review the applicable rule, current energy sources and assigned roles when setting up each shutdown. Check that the devices fit the isolation points and that the tags identify what is under work. Give incoming crews a way to verify the status through the designated site contact before they begin or request restoration.
Frequently Asked Questions
Does OSHA 1910.147 Apply to Construction?
Federal OSHA’s 1910.147 expressly excludes construction employment. For construction electrical work, check Subpart K, including 1926.417 when its circuit and equipment provisions apply. For covered concrete or masonry equipment repair and maintenance, review 1926.702(j) for the lockout and tagging requirement.
What Does LOTO Mean in Construction?
LOTO stands for lockout/tagout. It describes using physical controls and warnings to protect people against unintended operation or hazardous energy during covered work. The equipment, task and applicable rule determine the specific controls, so crews should follow the jobsite’s approved procedure.
What Lockout Devices Do Construction Crews Need?
Start with the documented isolation points, then select devices that fit those points and work under the site procedure. Depending on the application, a kit may include safety padlocks, hasps, breaker or plug lockout devices, and warning tags. Have the responsible lead confirm equipment fit and the tag wording before the kit goes out to the crew.